11 Dec 2020
By David Marsh
Boilerplate terms of contracts can have a significant impact on the conduct of construction disputes.

This is a short article regarding two dissimilar cases, both of which focus attention on the fact that the boilerplate terms of contracts can have a significant impact on the conduct of construction disputes. Our experienced construction law team can help avoid issues with construction disputes and more.

Tianqi Lithium

The first decision comes from the arbitration realm in which the Court of Appeal of the Western Australian Supreme Court dismissed an appeal from a decision of Master Sanderson not to grant a stay of proceedings under s.8 of the Commercial Arbitration Act 2012 (WA) in Tianqi Lithium Kwinana Pty Ltd v MSP Engineering Pty Ltd [No 2] [2020] WASCA 201.  It is a reasonably important decision on the question of how one reads the limited preservation of rights provisions in dispute resolution clauses.  By this I mean, most construction contracts have dispute resolution clauses and, even where arbitration is prescribed, there is (at least) some protection for the right to seek urgent relief from a court.

In this case, the contract in issue was an Australian Standard AS 4902 that had been slightly modified.  Relevantly, the standard preservation provision in clause 42.4 of the dispute resolution remained unamended.  As a reminder, that clause provides:

Nothing herein shall prejudice the right of a party to initiate proceedings to enforce payment due under the contract or to seek injunctive or urgent declaratory relief. [Emphasis added] 

It is also worthy to note that the standard right of set-off provision in clause 38.2 had been removed, although the withholding of payment provisions in termination were obtained in clause 39.10.

After analysing the authorities on how one reads clauses like clause 42.4, when dealing with a stay application under s.8 of the Act (and after considering three possible ways of doing so), the Court of Appeal adopted the following test at paragraph [127]:

… ‘proceedings to enforce payment due’ under the contract is proceedings which are capable of summary determination: ie, proceedings in which there is no triable issue which would form a proper basis for defending a summary judgment application.

This seems to be a sensible outcome for the reasons given by the Court of Appeal.  It is, however, still a matter of contractual interpretation and it might be open for parties to expand the rights of set‑off or to reduce the ambit of the preservation provision in the future so as to circumvent or minimise the impact of this decision.

BCS Infrastructure v Jones Lang Lasalle

The second decision (and an even better example of paying attention to the boilerplate) comes from the Supreme Court of Victoria where Her Honour Justice Stynes handed down an interesting decision in the matter of BCS Infrastructure v Jones Lang Lasalle (NSW) Pty Ltd [2020] VSC 379 regarding service of payment claims under the Victorian SOP Act.

The difference between jurisdictions on service (amongst other things) are such that, from a Western Australian perspective, a detailed analysis of the decision is not warranted.  However, the issue of service of payment claims and adjudication applications has long vexed the SOP regime across all Australian jurisdictions such that one wonders whether it might be something best dealt with by Parliament, preferably under uniform legislation dealing with the question of valid service.  I note that there is a provision in Western Australia relating to service but it may not go as far or be as clear as it ought to.

In this case, the various claims underpinning the SOPA application were provided through a document sharing platform called Corrigo and was attached to an invoice, notwithstanding the fact that the parties had been communicating by email with respect to unpaid invoices beforehand.  Indeed, her Honour found that this was the first time that the builder had used Corrigo to upload these kinds of documents.

The question for the Court was whether the relevant date, for the purpose of the date by which the principal had to respond to the application under the Victorian Act, was the date upon which the claims were uploaded to Corrigo or the date upon which the claim came to the attention of the principal. If the former, the principal would have been liable for the entire amount of the claim. Her Honour, after working through the history of the communications between the parties and the notice provisions of the relevant contract, found that the time by which the respondent had to respond to the payment claim was calculated from the latter date, when it came to the attention of the principal.  The effect of her Honour’s finding was that the respondent’s response to the payment claim was within time.

In the end, despite the relatively fact-heavy analysis conducted by her Honour, there is a simple takeaway for all practitioners and that is, to pay close attention to the notice provisions of the contract.  This also extends to other administrative provisions of the contract because these provisions might also affect how the claim must be prepared and delivered.  For example, if the building contract provides for the SOPA claim to be delivered to a specific appointor body, it should be served on that appointor, and failure to do so might render the claim nugatory.  In summary, bringing and defending SOPA claims (which in and of themselves can be quite complex) is often done against significant time pressure such that parties might forget to dot the i’s and cross the t’s of the application.  Anyone working in the area, as we do, need to have simple processes in place to make sure that the contractual requirements, as well as the requirements of the relevant SOP legislation, are met.


Recent Insights

SOPA Not So Super?

As the Building and Construction Industry (Security of Payment) Act 2021 (“SOPA”) continues in its infancy alongside the Constructions Contracts...
Read More

Two Percenters & the Intransigent Opponent

While the vast majority of cases settle before trial, even the most well-prepared cases can face an intransigent opponent. This...
Read More

Best Lawyers Recognition for Doug Solomon

We are pleased to share that our Doug Solomon has once again been recognised by Best Lawyers and, together with...
Read More

Unravelling Time-Bars – SOPA WA

As the dust slowly settles post the August 2022 introduction of WA’s new SOP Act, we’ve taken a bit of...
Read More

How To Make Your Contract Terms Stick

If you're involved in drawing up contracts but not an expert in Contract Law, our article below will assist you....
Read More

Building Defects – How & When to Make a Claim

Unfortunately, building and defects go hand in hand. Whether you are the owner of the building built or a subsequent...
Read More

How to Respond to a Statutory Demand

In this article, we explain what a statutory demand is, the legal consequences of receiving one, and how you can...
Read More

How To Build a Security Of Payments Act Claim and Response

Following recent amendments to the WA Building and Construction Act, claimants and respondents alike may be left asking how these...
Read More

Infrastructure expenditure affecting the Western Australian construction market

Over the last 12 months, there have been numerous reports of a skills shortage in the Western Australian building and...
Read More

Are you SOPA Ready?

This week (on 22 June 2021), amendments to the WA regime as set out in the Building and Construction Industry...
Read More

Get in touch with our Construction Law Team

DAVID MARSH

Partner Litigation

JIM ZEAKIS

Senior Associate